A) Physical estimates or surveys of the work performed to date.
B) The work plan basis, which uses the project management plan to calculate the percentage of the construction completed.
C) The billings basis, using the proportion that progress billings to date bear to the total estimated billings for the contract.
D) Physical estimates or surveys of the work performed to date and the billings basis, using the proportion that progress billings to date bear to the total estimated billings for the contract.
E) All of the given answers.
Correct Answer
verified
Multiple Choice
A) The amount of contract revenue recognised as revenue must be disclosed either on the face of the income statement or in the accompanying notes.
B) Contract costs incurred must be disclosed either on the face of the income statement or in the accompanying notes.
C) A liability being the gross amount due to customers for contract work.
D) The gross amount of work progress must be disclosed in the balance sheet.
E) For contracts in progress, the amount of advances received, must be disclosed either on the face of the income statement or in the accompanying notes.