When considering whether to move the project to its optimum cost-time position, the manager should also consider ________.

Correct Answer

verifed

verified

risk
Explanation: Should the p...

View Answer

When adding resources, there are limits as to how much speed can be gained.

A) True
B) False

Correct Answer

verifed

verified

Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by


A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

An activity must be crashed on each critical path in order to reduce project duration.

A) True
B) False

Correct Answer

verifed

verified

The total cost for each time unit of a project is the sum of labor, materials, and equipment.

A) True
B) False

Correct Answer

verifed

verified

Compressing activities on a project with a sensitive project network will:


A) Increase risk of delaying the project.
B) Improve cost-time crashing success.
C) Reduce scheduling flexibility.
D) Increase risk of delaying the project and reduce scheduling flexibility.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by


A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Incentive contracts can make the reduction of project time rewarding-usually for both the project contractor and owner.

A) True
B) False

Correct Answer

verifed

verified

The ________ project cost is the sum of the indirect and direct costs.

Correct Answer

verifed

verified

total
Explanation: T...

View Answer

If indirect costs are a significant percentage of total project costs, reductions in project time can represent very real savings.

A) True
B) False

Correct Answer

verifed

verified

Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by


A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is NOT considered a project indirect cost?


A) Supervision
B) Consultants
C) Equipment
D) Interest
E) The project manager's salary

F) C) and E)
G) B) and C)

Correct Answer

verifed

verified

It is going to cost $80,000 a day simply to house and feed a construction crew in the farthest reaches of northern Alaska.This would be an example of a situation requiring reducing the project duration due to


A) Imposed project deadlines.
B) Time to market.
C) Unforeseen project delays.
D) High overhead.
E) Incentive contracts.

F) C) and E)
G) B) and D)

Correct Answer

verifed

verified

Which of the following is NOT a rational reason to reduce project duration?


A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

As a project is crashed and project duration is reduced, direct costs typically


A) Increase.
B) Become unstable.
C) Decrease.
D) Become unreliable.
E) Stay the same.

F) A) and D)
G) A) and E)

Correct Answer

verifed

verified

When crashing a schedule, this may set in when a least-cost method is used.


A) increased risk
B) fatigue and resentment
C) increased cost
D) decrease in available management reserve

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

Resources are frequently over-allocated when crashing a schedule.

A) True
B) False

Correct Answer

verifed

verified

Given that an activity's normal time and cost are 10 days and $400, respectively, and its crash time and cost are 5 days and $800, respectively, what is the activity's slope?

Correct Answer

verifed

verified

Crash cost per time unit equal...

View Answer

One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making.

A) True
B) False

Correct Answer

verifed

verified

When reducing project duration, there will always be an optimum cost-time point where the total cost of the project is less than it was when the project was initially planned under normal conditions.

A) True
B) False

Correct Answer

verifed

verified